Construction of Shillong Business cum Tourism

 

  • Name of the contractor - M/s Badri Rai & Company
  • Date of contract award - 25th November 2021
  • Expected date of completion - 31st March 2025
  • Financial Progress as of end of November 2024 - 77.78 %
  • Physical Progress as of end of November 2024 - 75 %

 

Actual photograph of project site at month of November 2024 (Work in Progress)