Megamenu

 

Construction of 6 KM Smart Roads

 

  • Name of the contractor - M/s Dhar Construction Company
  • Letter of award - 22nd December 2021
  • Expected date of completion - 31st December 2024
  • Financial Progress as of end of September 2024 - 20.27 %
  • Physical Progress as of end of September 2024 - 27 %

 

Actual photograph of project site at month of September 2024 (Work in Progress)