Megamenu

 

Construction of Polo Commercial Complex.

 

Contractor for Construction of Commercial Complex at Polo, Shillong, has been appointed and have started construction activities from November 2020.

  • Name of the contractor - M/s Badri Rai and Company
  • Date of contract award - 21st August 2020
  • Expected date of completion - Completed
  • Financial Progress as of end of November 2024 - 89.66%
  • Physical Progress as of end of November 2024 - 98 %

 

Actual photograph of project site at month of November 2024 (Work in Progress)