Megamenu

 

Development of office cum automated Multi-Level Car Park (on DBOT Basis)

 

  • Name of the contractor - M/s. Shri Aloysius Arengh in JV with M/s. LT Elevator Private Limited
  • Date of contract award - 9th January 2023
  • Expected date of completion - 30th June 2026
  • Financial Progress as of end of January 2026 - 40.14 %
  • Physical Progress as of end of January 2026 - 60 %

 

Actual photograph of project site at month of January 2026 (Work in Progress)