Retrofitting and Upgradation of 3 Multilevel Car Park

 

  • Name of the contractor - Sri. Avantika Contractor (I) Limited
  • Date of contract award - 28th March 2022
  • Expected date of completion - 31st March 2025
  • Financial Progress as of end of September 2024 - 13.63 %
  • Physical Progress as of end of September 2024 - 22 %

 

Actual photograph of project site at month of September 2024 (Work in Progress)