Mechanised Multi Level Car Park MLP at Motphran in Shillong

 

  • Name of the contractor - M/s L.T Elevator Pvt Ltd in JV with M/s Bungsing Sohphoh.
  • Date of contract award - 26th March 2022
  • Expected date of completion - 30th June 2026
  • Financial Progress as of end of January 2026 - 28.77 %
  • Physical Progress as of end of January 2026 - 45 %

 

Actual photograph of project site at month of January 2026 (Work in Progress)